US Navy Issues HII RFP for Two Ford-class Aircraft Carriers

The US Navy released a CVN 80/81 two-ship buy Request for Proposal (RFP) to Huntington Ingalls Industries - Newport News Shipbuilding (HII-NNS) March 19 to further define the cost savings achievable with a two-ship buy.


The US Navy released a CVN 80/81 two-ship buy Request for Proposal (RFP) to Huntington Ingalls Industries - Newport News Shipbuilding (HII-NNS) March 19 to further define the cost savings achievable with a two-ship buy.


US Navy Issues HII RFP for woFord class Aircraft Carriers 001 The aircraft carrier Pre-Commissioning Unit (PCU) Gerald R. Ford (CVN 78) pulls into Naval Station Norfolk for the first time
(Credit: US Navy)


With lethality and affordability a top priority, the Navy has been working with HII-NNS over the last several months to estimate the total savings associated with procuring CVN 80 and CVN 81 as a two-ship buy.

"In keeping with the National Defense Strategy, the Navy developed an acquisition strategy to combine the CVN 80 and CVN 81 procurements to better achieve the Department's objectives of building a more lethal force with greater performance and affordability," said James F. Geurts, Assistant Secretary of the Navy, Research Development and Acquisition. "This opportunity for a two-ship contract is dependent on significant savings that the shipbuilding industry and government must demonstrate. The Navy is requesting a proposal from HII-NNS in order to evaluate whether we can achieve significant savings."

The two-ship buy is a contracting strategy the Navy has effectively used in the 1980s to procure Nimitz-class aircraft carriers and achieved significant acquisition cost savings compared to contracting for the ships individually. While the CVN 80/81 two-ship buy negotiations transpire, the Navy is pursuing contracting actions necessary to continue CVN 80 fabrication in fiscal year (FY) 2018 and preserve the current schedule. The Navy plans to award the CVN 80 construction contract in early FY 2019 as a two-ship buy pending Congressional approval and achieving significant savings.

Enterprise (CVN 80) is the third ship of the Gerald R. Ford class and the numerical replacement for USS Eisenhower (CVN 69). CVN 81, not yet named, will be the fourth ship of the class and will be the numerical replacement for USS Carl Vinson (CVN 70). CVN 80 began advanced planning and initial long-lead-time material procurement in May 2016.